VANDERBURGH COUNTY

BOARD OF COMMISSIONERS

SPECIAL JAIL BID OPENING MEETING

September 23, 2003


The Vanderburgh County Board of Commissioners met in special session this 23rd day of September, 2003 at 4:04 p.m. in Room 307 of the Civic Center Complex to open bids for the jail project with President David Mosby presiding.


Call to Order

 

President Mosby: Call to order Board of Commissioners meeting of Vanderburgh County, September 23, 2003. Introductions are as follows; to my far right, Paul Summers from United Consulting; Tammy McKinney, Superintendent of Buildings; Kevin Winternheimer, Counselor; Commissioner Fanello; myself, Commissioner Mosby; Commissioner Crouch; and Madelyn Grayson, Recording Secretary. If everybody would, please stand and say the Pledge.


(The Pledge of Allegiance was given.)


President Mosby: Thank you very much.


Permission to Open Bids for the Vanderburgh County Jail


President Mosby: Action items, we have one item on the agenda for today. That one item will be bid advertisements and openings for the county jail. At this time I would take a motion for permission to open bids for the county jail.


Commissioner Fanello: Motion to open bids.


Commissioner Crouch: Second.


President Mosby: I have a motion and a second to open bids. So ordered. At this time I will turn it over to counselor, Kevin Winternheimer. Before I start, does anyone in the audience have a bid for me to open today. Seeing none, we will start.


President Mosby: Is there any bids in the hall?


Commissioner Fanello: Do you want to check in the hallway?


President Mosby: Check the hall. At this time I also would like to say that County Auditor, Bill Fluty, is present.


Contract No. 1: Multi-Scope Bid Package


Kevin Winternheimer: Seeing no other bids, we’ll start with the multi-scope bid package that’s item number one. The first bid is from Deig Brothers Lumber and Construction Company, Inc. of Evansville. Okay, their bid is, the base bid is $18,294,000. Alternate number one, $150,446. Alternate number two, $168,208. Alternate number three, $257,997. Alternate number four, $936,058. Alternate number five, $205,740. Alternate number six, $134,784. Alternate number seven, $23,198. Alternate number eight, they did not bid, and they did not bid alternate number nine. The next bid is from Industrial Contractors, Inc. of Evansville. The base bid, $18,560,618. Alternate number one, $280,760. Alternate number two, $192,705. Alternate number three, $287,191. Alternate number four, $874,136. Alternate number five, $196,678. Alternate number six, $134,337. Alternate number seven, $30,474. Alternate number eight and nine they have no change listed. The next bid is from Weddle Brothers Building Group LLC from Bloomington, Indiana. Base bid, $15,700,000. Alternate number one, $186,000. Alternate number two, $104,000. Alternate number three, $280,000. Alternate number four, $805,000. Alternate number five, $225,000. Alternate number six, $133,000. Alternate number seven, $30,000, and no bid on eight and nine. We have one more on the multi-scope. The next bid is from Williams Brothers Construction, Inc. of Peoria, Illinois. Base bid, $15,250,000. Alternate number one, $220,000. Alternate number two, $126,000. Alternate number three, $262,000. Alternate number four, $768,000. Alternate number five, $224,000. Alternate number six, $132,000. Number seven, $22,000. Eight and nine is a no bid. Is that all we have on the multi-scope, then?


Contract No. 1: Multi-Scope Bid Package

Contractor

Deig Brothers

Industrial Contractors

Weddle Brothers

(Bloomington, IN)

Williams Brothers (Peoria, IL)

Base Bid

$18,294,000

$18,560,618

$15,700,000

$15,250,000

Alternate No. 1

$150,446

$280,760

$186,000

$220,000

Alternate No. 2

$168,208

$192,705

$104,000

$126,000

Alternate No. 3

$257,997

$287,191

$280,000

$262,000

Alternate No. 4

$936,058

$874,136

$805,000

$768,000

Alternate No. 5

$205,740

$196,678

$225,000

$224,000

Alternate No. 6

$134,784

$134,337

$133,000

$132,000

Alternate No. 7

$23,198

$30,474

$30,000

$22,000

Alternate No. 8

No Bid

No Bid

No Bid

No Bid

Alternate No. 9

No Bid

No Bid

No Bid

No Bid


Contract No. 2: Kitchen Equipment Bid Package


Kevin Winternheimer: Going next to the kitchen equipment package. The first bid is submitted by C & T Design and Equipment Company, Inc. of Indianapolis. Base bid, $622,297. Alternate, let’s see, there are no alternates bid on this. Okay, the next bid is submitted by Great Lakes Hotel Supply Company from Detroit, Michigan. Base bid, $603,159. No alternates on that. The last bid on the kitchen equipment is from the Wasserstrom Company from Cincinnati, Ohio. Base bid, $607,305. No alternates on that.


Contract No. 2: Kitchen Equipment Bid Package

Contractor

Base Bid

Alternates

C & T Design & Equipment Company, Inc. (Indianapolis)

$622,297

No alternates bid.

Great Lakes Hotel Supply Co. (Detroit, MI)

$603,159

No alternates bid.

Wasserstrom Company (Cincinnati, OH)

$607,305

No alternates bid.


Contract No. 3: Mechanical Bid Package


Kevin Winternheimer: Next is the mechanical bid package. The first one is from Industrial Contractors, Inc. of Evansville. Base bid, $4,394,378. Alternate number one, $54,142. Alternate number two, $62,123. Alternate number three, $53,230. Alternate number four, $266,496. I’ll repeat that, this is alternate number four, $266,496. Alternate number five, no change. And for six, seven, eight and nine they have written no change. The next bid is from Peyronnin Construction Company, Inc. of Evansville. Base bid, $4,190,000. Alternate number one, $48,500. Number two, $58,500. Number three, $56,700. Number four, $218,400. Number five, six, seven, eight and nine they have written no change.


Paul Summers: Is this the last one?


Kevin Winternheimer: The last bid on the mechanical bid package is from Precision Piping and Mechanical, Inc. of Evansville. Base bid, $4,449,980. Alternate number one, $52,000. Alternate number two, $70,000. Number three, $53,500. Number four, $186,000. Five, six, seven, eight and nine they have written N/A.


Contract No. 3: Mechanical Bid Package

Contractor

Base Bid

Alt. 1

Alt. 2

Alt. 3

Alt. 4

Alt. 5-9

Industrial Contractors

$4,394,378

$54,142

$62,123

$53,230

$266,496

No Bid

Peyronnin Construction

$4,190,000

$48,500

$58,500

$56,700

$218,400

No Bid

PPMI Construction Co.

$4,449,980

$52,000

$70,000

$53,500

$186,000

No Bid


Contract No. 4: Electrical Bid Package


Kevin Winternheimer: Now, going to the electrical bids. The first one is from Deig Brothers Lumber and Construction Company, Inc. of Evansville. Base bid, $3,549,000. Alternate number one, $34,500. Number two, $28,500. Number three, $35,000. Number four, $96,000. Five, six, seven and eight they have, they’ve types N/A. Alternate number nine, they have a deduct of $6,000. The next bidder is Industrial Contractors, Inc. of Evansville. Base bid, $3,932,946. Alternate number one, $20,045. Alternate number two, $12,899. Number three, $26,000. Number four, $81,778. Number five, no change, as is six and seven. Under alternate eight, they have $2,721. Number nine, they have $7,762. The next bid is from Mel-Kay Electric Company, Inc. of Evansville. Base bid, $3,082,000. Alternate number one, $31,212. Alternate number two, $28,420. Number three, $31,725. Number four, $86,000. Number five, six, seven and eight, they have N/A. Alternate number nine, is a deduct of $3,200. The next bid is from Mounts Electric, Inc. of Evansville. Base bid, $3,783,000. Alternate number one, $32,031.65. Alternate number two, $17,622.70. Number three, $23,510.25. Alternate number four, $64,339.20. Five through eight are blank. Number nine is a deduct of $5,000. The next bid is from Premier Electric, Inc. of Evansville. Base bid, $3,860,000. Alternate number one, $64,000. Number two, $17,500. Number three, $18,500.

Number four, $102,105. Alternate number five, six, seven and eight are no bids. Number nine is a deduct of $4,000. The last bid on the electrical, the bidder is The State Group Industrial USA Limited from Evansville, Indiana. Base bid, $3,373,892. Alternate number one, $33,000. Number two, $26,960. Number three, $43,179. Number four, $89,345. Five, six, seven and eight, they’ve written N/A. Under number nine it says no change, no cost, no credit.


Contract No. 4: Electrical Bid Package

Contractor

Deig Brothers

Industrial Contractors

Mel-Kay Electric

Mounts

Electric

Premier Electric

The State Group Industrial USA

Base Bid

$3,549,000

$3,932,946

$3,082,000

$3,783,000

$3,860,000

$3,373,892

Alternate 1

$34,500

$20,045

$31,212

$32,031.65

$64,000

$33,000

Alternate 2

$28,500

$12,899

$28,420

$17,622.70

$17,500

$26,960

Alternate 3

$35,000

$26,000

$31,725

$23,510.25

$18,500

$43,179

Alternate 4

$96,000

$81,778

$86,000

$64,339.20

$102,105

$89,345

Alts. 5-8

No Bid

5-7 No Bid

#8 $2,721

No Bid

No Bid

No Bid

No Bid

Alt. No. 9

Deduct $6,000

$7,762

Deduct

$3,200

Deduct

$5,000

Deduct

$4,000

No Change



Contract No. 5: Security Electronics Bid Package


Kevin Winternheimer: Next is the security electronics bids. Okay, the first bid is from Accurate Controls, Inc. of, I hope I pronounce it correctly, Ripon, R-i-p-o-n, Wisconsin. Base bid, $734,600. Alternate number one, $3,300. Number two, $300. Number three, $15,300. Number four, $30,700. Number five, six and seven they have printed N/A. Alternate number eight, $68,200. Number nine they have written N/A. Okay, the next bid is from Stanley Security Solutions, Inc., from Noblesville, Indiana. She wants me to add this is the Integrator.com division. Base bid, $468,900. Alternate number one, $2,300. Number two, $400. Number three, $10,200. Number four, $15,700. Beside five, six and seven they’ve written N/A. Alternate number eight, $26,950. Beside number nine they have written N/A. Next bidder, MASK Systems, Inc. from Moorpark, California. Base bid, $1,067,750. Alternate number one, $6,500. Number two, $2,800. Number three, $6,000. Number four, $11,500. Number five, they’ve typed not applicable to bid. They put the same thing for six and seven. Number eight, they have $74,088. Number nine it says not applicable. The next bid is from Norment Security Group, Inc., from Montgomery, Alabama. Base bid, $859,000. Alternate number one, $2,000. Number two, $1,000. Number three, $2,000. Number four, $16,000. Number five, they’ve typed in no change, as they did for six and seven. Alternate number eight, $43,000. Alternate number nine they’ve typed in no change. The next bid is by Pinnacle Electronic Systems, Inc., from Westchester, Pennsylvania. Base bid, $749,000. Alternate number one, $9,523. Number two, $7,907. Number three, $8,466. Number four, $23,931. They left five, six and seven blank. Alternate number eight, $79,540. They did not have an item number nine that I can see. Unless it’s somewhere in here. It wasn’t with the others. Okay, moving on, the next bid Southwestern Communications, Inc., Decatur, Alabama. Base bid, $688,569. Alternate number one, $3,889. Number two, $1,921. Number three, $23,482. Number four, $40,492. Number five is blank, as is six and seven. Number eight, $31,103. Number nine is blank. Is that all of those?



Contract No. 5: Security Electronics Bid Package

Contractor

Base Bid

Alt. 1

Alt. 2

Alt. 3

Alt. 4

Alt. 5-7

Alt. 8

Alt. 9

Accurate Controls, Inc.

(Ripon, Wisconsin)

$734,600

$3,300

$300

$15,300

$30,700

No Bid

$68,200

No Bid

Integrator.com (Noblesville, IN)

(Stanley Security Solution)

$468,900

$2,300

$400

$10,200

$15,700

No Bid

$26,950

No Bid

MASK Systems, Inc.

(Moorpark, California)

$1,067,750

$6,500

$2,800

$6,000

$11,500

No Bid

$74,088

No Bid

Norment Security Group, Inc.

(Montgomery, Alabama)

$859,000

$2,000

$1,000

$2,000

$16,000

No Bid

$43,000

No Bid

Pinnacle Electronic Systems

(Westchester, Pennsylvania)

$749,000

$9,523

$7,907

$8,466

$23,931

No Bid

$79,540

No Bid

Southwestern Communications

(Decatur, Alabama)

$688,569

$3,889

$1,921

$23,482

$40,492

No Bid

$31,103

No Bid


Combination Bids


Kevin Winternheimer: Combination bids? Apparently under the combination bid category we have two envelopes. Okay, the first one is from Deig Brothers Lumber and Construction Company, Inc. of Evansville. Base bid, twenty–


Unidentified: (Inaudible. Not at mike.)


Kevin Winternheimer: Oh, I’m sorry, I see what you...okay, I’m sorry. This is choosing the contracts, I guess, the components. This is contract numbers one and four. It’s still Deig Brothers. Again, one and four. Now the base bid for those items, $21,783,000. Under the alternates, alternate number one, $184,946. Number two, $196,708. Number three, $292,997. Number four, $1,032,058. Number five, $205,740. Number six, $134,784. Number seven, $23,198. Under alternate number eight they’ve typed N/A. Number nine, deduct $6,000. We have one more. This is from Industrial Contractors, Inc. of Evansville.


Paul Summers: It should be on the outside of the envelope.


Kevin Winternheimer: Let’s look and see if it’s on here. Is anyone from Industrial here.


Unidentified: I believe it’s one, three and four.


Kevin Winternheimer: Okay. He thinks it’s one, three and four. In any event, I’m going to read the numbers. It may be in some of that other information in the packet. Base bid, $26,485,326. Under alternate number one, $359,492. Number two, $272,571. Number three, $370,700. Number four, $1,243,451. Number five, $196,678. Number six, $134,337. Number seven, $30,474. Number eight, $2,721. Number nine, $7,762. That is all the bids we have.








Combination Bids

Contractor

Deig Brothers

(Contracts 1 & 4)

Industrial Contractors

(Contracts 1, 3 & 4)

Base Bid

$21,783,000

$26,485,326

Alternate No. 1

$184,946

$359,492

Alternate No. 2

$196,708

$272,571

Alternate No. 3

$292,997

$370,700

Alternate No. 4

$1,032,058

$1,243,451

Alternate No. 5

$205,740

$196,678

Alternate No. 6

$134,784

$134,337

Alternate No. 7

$23,198

$30,474

Alternate No. 8

No Bid

$2,721

Alternate No. 9

Deduct $6,000

$7,762

  

President Mosby: Is there any questions by any Commissioners? Seeing none, chair would entertain a motion to take bids under advisement.


Commissioner Fanello: Motion to take bids under advisement.


Commissioner Crouch: Second.


President Mosby: I have a motion and a second to take bids under advisement. So ordered.


Commissioner Fanello: Motion to adjourn.


Commissioner Crouch: Second.


President Mosby: I have a motion and a second to adjourn. We stand adjourned at 4:40 p.m.


(The meeting was adjourned at 4:40 p.m.)


         Those in Attendance:

         David W. Mosby             Catherine Fanello           Suzanne M. Crouch

         Bill Fluty                          Kevin Winternheimer      Tammy McKinney

         Madelyn Grayson           Paul Summers                Others Unidentified

         Members of Media 